Filed under Other Projects

Multiple Lane closures planned for Rotunda at Oakwood

Please be advised there are several lane closures scheduled for the Rotunda and Oakwood intersection: Beginning Friday, September 14, there is a single lane closure of a portion of Rotunda at the Oakwood intersection. Beginning Wednesday, September 19, there will be a five-lane closure through the intersection. Only one lane in each direction will be … Continue reading

Rotunda right lane closure at Oakwood

The contractor  is scheduling  a right lane closure on Rotunda at Oakwood to begin Friday, September 14, 2018.  The closure is needed for the 60-inch storm sewer installation project. Thank you for your patience while we build a better Dearborn.

Oakwood Boulevard Construction

Phase I — Oakwood from Pelham to Rotunda Drive: Weather permitting, the week of August 6, the contractor will begin the deep storm sewer/water main construction on Oakwood Boulevard from Pelham to Rotunda Drive. Phase II — Oakwood from Rotunda Drive to Vince Avenue: Weather permitting, the week of August 6, the contractor will be working … Continue reading

Wyoming Avenue Resurfacing Project

The Wayne County Department of Public Services is planning to Resurface Wyoming Ave. from Ford Rd. to 250 ft. North of Conrail Railroad. Weather permitting, the contractor will begin work the week of Monday July 16 with a tentative completion date of Oct. 15. One lane of traffic each direction will be maintained at all … Continue reading

Hubbard Drive Construction Update

Residents of Korte, Westland, Helen, Palmer and Curtis Streets, please be aware: On Tuesday, July 10, weather permitting, the contractor will be cold-milling westbound Hubbard Drive from Mercury to Greenfield. This is finishing work from last year’s project by International Transmission Company (ITC). Access to Rosalie and Helen Streets as well as garages of Hubbard … Continue reading

Nowlin Street reopened

All lanes of Nowlin Street have reopened as of Nov. 24 after closing for resurfacing in October. Traffic has resumed as normal. Thank you for your patience during this project.

Rotunda closed at Greenfield for bridge repair

Starting Aug. 4, Rotunda at Greenfield will be closed for bridge repair for approximately five weeks. The road will reopen on or around Sept. 8, weather permitting. Rotunda traffic will be diverted onto the ramps over Greenfield and then back onto Rotunda.