Sewer Separation 2015-2016 Schedule

Combined Sewer Overflow construction will begin in March 2015 in the Crowley Park neighborhood, bounded by Telegraph Road west to Westwood Street, and Michigan Avenue south to Dartmouth Street.

Stay informed about this project through updates on this website. Sign up in the menu on the right-hand side of the page to receive updates via email.

2015 Proposed Construction
Phase 1 of the project will begin in March 2015, and will include the following streets:

  • Bailey Street from Dartmouth to Princeton
  • Banner Street from Dartmouth to Princeton
  • Penn Street from Westwood to Telegraph
  • Notre Dame Street from Westwood to Telegraph
  • Homeplace Street from Princeton to Oxford
  • Burns Street from Princeton to Oxford
  • Princeton Street from Banner to Telegraph

2016 Proposed Construction
Phase 2 of the project will begin in March 2016 and will include the following streets:

  • Princeton Street from Westwood to Banner
  • Cherry Street from Westwood to Bailey
  • Dunning Street from Westwood to Bailey
  • Oxford Street from Westwood to Telegraph
  • Hickory Street from Westwood to Bailey
  • Cooke Street from Westwood to Bailey
  • Scott Street from Bailey to Telegraph
  • Westwood Street from Oxford to the railroad tracks
  • Bailey Street from Princeton to the railroad tracks
  • Homeplace Street from Oxford to the railroad tracks
  • Boldt Street from Princeton to the railroad tracks

Refer to the map below for details on the timeline of construction in this area. Please note that all dates are tentative, subject to weather and other factors.

If a project will specifically impact your home, such as by preventing access to your driveway for a day, a notification letter will be placed on or near your front door.

If you have questions regarding the project north of Cherry Hill, please call Construction Engineering Technician Dylan Abbas at 313-801-8575.